Mega Project Brenner Base Tunnel: First Milestone Achieved with Herrenknecht Tunnel Boring Machine
Aug 27, 2020
A first major step has been taken in the construction of the world's longest underground rail link with a length of twice 64 kilometers in total. In July, with the completion of the 16.7 km long exploratory tunnel, proud tunnelers at the Brenner Base Tunnel celebrated the first decisive breakthrough of a Herrenknecht tunnel boring machine. A key structure for sustainable trans-European freight and passenger transport is being built on the north-south axis from Helsinki to Valletta.
8:27 a.m. early Monday morning, July 6, 2020: precise and confident, internationally experienced miners crack the last centimeters of rock with their tunnel boring machine. With the precision targeted breakthrough into the cavern on the Austrian side of the new Brenner tunnel, the first main breakthrough was achieved with a Herrenknecht tunnel boring machine (TBM).
A groundbreaking signal for what is currently the largest European railway infrastructure project and an emotional high point for the hard-working tunnel builders, engineers and project managers on this day: "We reached our target with pinpoint accuracy," says Anton Ertl, overall site manager of the construction phase, visibly moved.
The ARGE Tulfes-Pfons (ATP) construction consortium, consisting of Austria's STRABAG AG and Italian contractor »webuild« (formerly Salini-Impregilo), and the Gripper TBM manufactured in Schwanau thus completed an unusual hard rock mission. They are pioneers in the production of a superlative railway infrastructure.
From October 2015, the tunnel boring specialists steadfastly drove hard rock machine "Günther" (Ø 7,910mm) 16.7 kilometers from north to south under up to 1,300 meters of alpine rock toward their target. The TBM's name is borrowed from Tyrolean governor Günther Platter. The machine is one of a total of six tunnel boring machines that international construction joint ventures have so far ordered from Herrenknecht AG in Schwanau, South Baden, for the new world record project.
Congratulations
Pat Cox, member of the European Commission and TEN-T coordinator for the SCAN-MED Corridor, congratulated the site crews and the many other project partners on their outstanding performance:
"I congratulate you on the breakthrough of the tunnel boring machine, another important step and milestone for the Brenner Base Tunnel. After its completion, the BBT will not only link Austria with Italy, but will be the centerpiece of the Scandinavian-Mediterranean Corridor, which extends from Finland to Malta."
Under the direction of the Austrian-Italian BBT SE, with the Brenner Base Tunnel and a total length of twice 64 kilometers, the longest underground rail link in the world is being created. It crosses beneath the Alps between Innsbruck in Austria and Franzensfeste (Fortezza) in Italy as a particularly efficient flat rail route, that is, without any notable, energy-consuming gradients. Leonore Gewessler, Austrian Federal Minister of Climate Action, Environment, Energy, Mobility, Innovation and Technology, explained the ecological benefits of the project:
"Currently, 72 percent of goods are transported by truck. This results in 2.5 million truck journeys a year over the Brenner Pass. So the Brenner Base Tunnel means a shift from truck to rail. This is not just good news for the climate, i.e. significant CO2 reductions, but also for the people of Tyrol, and with the Brenner Base Tunnel we will be able to increase the number of freight trains from 66 to 225 per day."
Dr.-Ing. E.h. Martin Herrenknecht, founder and Chairman of the Board of Management of Herrenknecht AG, is certain:
"61 meters and 4 centimeters in just 24 hours with a modern Gripper TBM – in May 2020 the tunnelers at the Brenner Base Tunnel were able to set a new record in hard rock tunnelling. We very much appreciate the trust our customers and the client place in our Herrenknecht technology. We are proud to be part of the next record-setting structure in the Alps after the Gotthard Base Tunnel."
Project features of the Brenner Base Tunnel exploratory tunnel (Gripper TBM S-932 Günther)
- Findings from driving the exploratory tunnel benefit the subsequent advance of the main tubes. They run 12 meters above the exploratory tunnel with an inner diameter of 8.1 meters.
- The exploratory tunnel will later serve as a drainage and service tunnel.
- DCRM (Disc Cutter Rotation Monitoring): the system developed by Herrenknecht for monitoring the rotational movement and temperature of the disc cutters allows optimization of tool maintenance intervals.
Herrenknecht sextet
For the Italian lot of the exploratory tunnel (south axis), Herrenknecht supplied a Double Shield TBM (diameter 6,800 mm) specialized in rapid tunnelling in stable rock. By July 2020, it had already bored 9 of a total of 14 kilometers from south to north. The customer here is BTC S.c.a.r.l. consisting of the companies Astaldi S.p.A., Ghella S.p.A., P.A.C. S.p.A. and Cogeis S.p.A.
Since May 2019, the Italian sections of the main tubes have been bored by two Herrenknecht Double Shield TBMs (diameter 10,650 mm), also under the direction of BTC S.c.a.r.l. These two machines had already covered 4.3 and 4.7 kilometers respectively by July 2020. Two Herrenknecht Single Shield TBMs (diameter 10,340 mm) are planned for the main tubes on the Austrian side.
Here the ARGE H51 Pfons-Brenner joint venture (PORR Bau GmbH – Tunnelbau, G. HINTEREGGER & SÖHNE Baugesellschaft m.b.H., ITINERA S.p.A., Società Italiana per Condotte d´Acqua S.p.A.) is responsible for the tunnelling. Tenders for additional mechanized machine drives are currently in preparation.
Group deliveries
The Herrenknecht Group has also supplied the large-scale Brenner Base Tunnel project with a belt conveyor system for the transport of excavated rock. Bochum-based H+E GmbH designed and manufactured a system consisting of 37 belt conveyors and four spreaders with a total length of over 60 kilometers. The entire system is controlled from a central control panel.
Additionally, Euroform S.r.l. is supplying formwork for the lining of machine-driven or conventionally advanced tunnels. For the Mauls lot, the SDS production and logistics management system for segment production comes from VMT GmbH. VMT supplied the TUnIS navigation systems for all six tunnel boring machines ordered to date – for the Gripper TBM also the newly developed TUnIS.mobile app for operating the navigation system from outside the control cabin.
Project data
Brenner Base Tunnel
MACHINE / PROJECT DATA TULFES-PFONS EXPLORATORY TUNNEL
Machine type: Gripper TBM S-932
- Diameter: 7,910mm
- Drive power: 3,500kW
- Drive length: 16,630m
- Geology: quartz phyllite, schist
- Client: Brenner Base Tunnel BBT SE
- Contractor: ARGE Tulfes-Pfons (STRABAG AG, webuild)
MACHINE DATA MAULS
Machine type: Double Shield TBM S-1054
- Shield diameter: 6,800mm
- Drive power: 2,800kW
- Drive length: 14,000m
Machine type: 2 x Double Shield TBM S-1071 / S-1072
- Shield diameter: 10,650mm
- Drive power: 4,200kW
- Drive length: 2 x 14,000m PROJECT DATA MAULS
- Geology: granite gneiss, granodiorite, mica schist, phyllite
- Client: Brenner Base Tunnel BBT SE
- Contractor: BTC S.c.a.r.l. (Astaldi S.p.A., Ghella S.p.A., P.A.C. S.p.A. and Cogeis S.p.A.)
MACHINE / PROJECT DATA Pfons - Brenner
Machine type: 2 x Single Shield TBM S-1211 / S-1212
- Shield diameter: 10,340mm
- Drive power: 4,200kW
- Drive length: 10,544m / 10,249m
- Geology: quartz phyllite, Graubünden shale
- Client: Brenner Base Tunnel BBT SE
- Contractor: ARGE H51 Pfons-Brenner (PORR Bau GmbH – Tunnelbau, G. HINTEREGGER & SÖHNE Baugesellschaft m.b.H., ITINERA S.p.A., Società Italiana per Condotte d´Acqua S.p.A.)
Herrenknecht AG
Herrenknecht AG is the only company worldwide to deliver tunnel boring machines for all geologies and in all diameters – ranging from 0.10 to 19 meters. The product range comprises tailor-made machines for traffic, supply and disposal tunnels, technologies for routing of pipelines, as well as additional equipment and service packages. Herrenknecht also manufactures drilling equipment for vertical and inclined shafts as well as deep drilling rigs.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Herrenknecht AG
Achim Kühn
Head of Group Marketing and Corporate Communications
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 7824 302 5400
Fax:
+49 7824 302 4730