Green light given for ‘super sewer’ to clean up London’s river
Oct 22, 2014
Thames Water has today been given the go-ahead to start building London’s ‘super sewer’ which will tackle the sewage pollution in to the tidal River Thames.
The 25km tunnel will run underground from Acton storm tanks in West London, and travel roughly the line underneath the river to Abbey Mills Pumping Station in East London, where it will connect to the Lee Tunnel. The sewage collected from the 34 most polluting discharge points along the tidal river in Central London, will then be taken via the Lee Tunnel to Beckton sewage works for treatment.
Last year, 55m tonnes of sewage polluted the tidal River Thames, far higher than the average 39m tonnes that discharges in a typical year. This was due to the exceptionally wet weather, which caused the combined sewerage system that London has, collecting rain water and sewerage water from drains, to fill up and pour into the river even more than normal.
With the weather of 2014 already proving to be wetter than a typical year, the amount of sewage which is going into the river is likely to once again be above average.
Andy Mitchell, chief executive of Thames Tideway Tunnel, said: “If the tunnel had been in operation last year, it would have captured 97% of the sewage that poured in to London’s river. Hardly a week goes by when untreated sewage isn’t pouring in to London’s river and we are pleased that we can now start to tackle this archaic problem. This is a huge project but it’s a huge problem, and we can now get on with tackling it. It’s no easy task, but we’re confident that we can deliver this project and still achieve our aim of minimising the impact on our customer bills.”
The Thames Tideway Tunnel will take seven years to build, and main construction can now start in 2016 as planned. The project has been given a Development Consent Order, or DCO, by the Government, to be built as proposed using 24 construction sites across London. It will involve using six tunnel boring machines from five drive sites and will directly create more than 4,000 jobs.
Mr Mitchell, who joined the project earlier this year from his previous role at Crossrail, added: “This DCO means we can improve London’s river for the benefit of Britain. We appreciate the impact our construction work will have on some communities near our sites, but we will continue to work with them to keep disruption to a minimum.”
Debbie Leach, chair of the river charity Thames 21, said: “I find it embarrassing that as a first-world nation, we pour our effluent into the river as if we do not have the understanding of what harm it can do, not only to our environment, but also to our communities like mine who take pleasure out of using the river for recreation. Let’s stop being so British and polite and avoiding the problem by pretending it’s not there, there is a problem and we need to tackle it – and if that costs me a small increase on my water bill, then that is a cost that is well worth paying.”
Baroness Jo Valentine, Chief Executive of London First, said: “The system we have currently does not have the capacity to cope with the existing population, let alone support a growing city. Whilst I believe in keeping costs for households as low as possible, I also find it a false economy to suggest there is a better value solution than the Thames Tideway Tunnel.”
The Thames Tideway Tunnel will be financed and delivered by an independent specialist company, separate to Thames Water and with its own licence from Ofwat. Interested investors are currently preparing bids for this company, with the successful bidder expected to be announced next summer.
The project will be paid for by Thames Water sewerage customers, who will see an increase of up to a maximum of £70-80 (in 2011 prices, excluding inflation), by the mid 2020s.
To hear more about why the Thames Tideway Tunnel is needed, visit www.youpootoo.co.uk, or for information on the project, visit www.thamestidewaytunnel.co.uk.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Thameswater
Stuart White
Vastern Road
RG1 8DB Reading, Berkshire
United Kingdom
Phone:
+44 (0)203 577 4364