Hard Rock Tunnel Boring Machines are cutting tunnels through the Pyrenees
Sep 09, 2013
Two high-tech Herrenknecht tunnel boring machines completed an endurance test with bravura during long-distance tunnelling through the Pyrenees. After a total of 8.2 kilometers tunnelling through hard rock, the target line was reached with the final breakthrough in April 2013. The resulting cross-border tunnel project will be used for a high-voltage line to connect the French and Spanish electricity network with each other.
The Herrenknecht tunnel boring machines "Canigou" and "Alberas" are compact powerhouses: Equipped with an installed power of 1,250kW, they have a torque of 2,000kNm with a cutterhead diameter of 4.3 meters. The tunnel boring machines have a length of 301 and 253 meters respectively and weigh 620 tonnes. The Double Shield TBMs started at their launch portals in March and October 2012 to pre-drill and construct the 8.2km long tunnel through the hard rock of the Catalan Pyrenees. "Alberas" begun its mission in La Jonquera in Spain. "Canigou" advanced towards its sister machine from Montesquieu-des-Albères in France. The two Double Shield TBMs from Herrenknecht were ordered by the Franco-Spanish joint venture, consisting of the tunnelling specialists Eiffage and Dragados. The challenge was to create an ambitious tunnel project within a demanding timeframe.
After 1.23 kilometers of tunnelling, "Canigou" reached the end of the lot, coming from France beneath the Massif des Albères, in March 2013. The "Canigou" machine was immediately dismantled in the protection of a tunnel section in stable rock without any lining under the supervision Herrenknecht specialists. After 7.01 kilometers of tunnelling "Alberas", coming from Spain, drove into the tunnel drilled by "Canigou" already on April 22, 2013, and the breakthrough was celebrated in superb style. The best drilling performance of the overall project was achieved by the tunnelling teams with the Herrenknecht-TBM "Alberas" on the Spanish side: 53.5 meters per day with up to 1,040 meters drilled and built tunnel per month. "Alberas" was also dismantled in the drilled tunnel, and the components were removed through the north portal. The physical connection for the exchange of electricity is thus completed.
The cross-border power lines that connect Spain with France and the rest of Europe need to be extended urgently. The four existing connections do not have sufficient capacity to cope with bottlenecks or to compensate for fluctuations resulting from the use of renewable energy sources. As part of the bi-national project "INELFE" (INterconexión ELéctrica Francia-España) a 64.5km long, ultra-modern high-voltage direct current transmission link (HVDC) is being installed from Baixas, near Perpignan in France to Santa Llogaia near Figueras in Spain. In the tunnel drilled by the two Herrenknecht tunnelling machines, the route passes under the Pyrenees on the Catalan Mediterranean coast.
Herrenknecht is the world's number 1 in mechanized tunnelling technology. Also when drilling through hard rock. Double Shield TBMs from Herrenknecht are specialists for high advance rates in hard rock. They combine the functional principles of the Gripper TBM and the Single Shield TBM in one machine. This combination of methods allows the installation of concrete segments in stable geological conditions parallel to the excavation work, thus achieving very high advance rates. Lining the tunnel with segments contributes significantly to the high quality and durability of the structure.
For the "INELFE" project Herrenknecht prepared the back-up systems of the two machines for double storage: Logistics and storage facilities were designed in such a way that segments and grout could always be stored on the machine for two ring building sequences. Thus, the machine operators were able to exploit the potential of the Double Shield principle, without being limited by possible shortages in the material logistics. Due to the design of the machine components it was possible to dismantle them within the excavated drilling diameter without having to break out an additional cavern. The INELFE tunnel runs to a large extent parallel to the Le Perthus railway tunnel, built by Eiffage TP and Dragados S.A. from 2005 to 2007 with two large Double Shield TBMs from Herrenknecht (Ø 9.9m, total tunnelling length 16.4km).
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0)7824 302-5400
Fax:
+49 (0)7824 302-5400