Large Up Size Pipe Replacement Beneath The West Highland Railway
Feb 26, 2013
Replacement by trenchless method » Pipe bursting, in general
A HammerHead® HB125 static pipe-bursting system, provided by U Mole was recently utilised by rail contractor Carillion to undertake an interesting and challenging project to replace a 450mm i.d. clayware sectional culvert running beneath the main railway line between Crianlarich and Oban.
Running at around 5m depth, the 450mm existing culvert needed to be not only replaced but also up-sized to 630mm with the replacement pipe being HDPE. Whilst the project at first appeared to be a straight replacement job, with the need to utilise a 730mm diameter expander behind the bursting head, an equivalent up-size of over 250mm diameter, the installation of the new pipe was not going to be easy.
Although the contractor had used the Hammerhead® HB125 on an earlier section of works on the West Highland rail route, given the massive up-size required for the new installation, operator training of Carillion personnel was completed by U Mole engineers prior to the works on site at project site at Taynuilt.
Other parts of the challenge on the Taynuilt site over and above the up-size required, was access and site preparation. To achieve the replacement installation site works were undertaken for 14 days before the bursting work could commence. This was because ground conditions at the site proved to be soft which meant the footings for the pipe bursting system had to be correctly constructed. The site also required the removal of a line of trees in the rail embankment. These site preparations of the launch and burst site had to be completed with imported stone etc. Also required was the environmental protection of local waterways in case of any hydraulic leaks etc.
Once the site prep was completed the job could be started. Carillion’s workforce was ultimately delighted at the ease of operation of the bursting system once set up. The bursting works, including machine set up were completed over the course of just two days. The actual simultaneous burst run and new pipe installation were actually completed in less than half a working with day no disturbance to the railway line on the embankment above. Looking ahead to a series of future bursts beneath the railway line members of the crew commented that they were looking forward to once again using the HB125 system.
In terms of the site set-up, another complication which was faced by the contractor was ensuring that launch pit face was able to resist the pulling forces of the bursting rig. Carillion’s Section Engineer for the works, Glen Henderson, had to develop a temporary jacking face system which was capable of distributing the pulling force of the rig against the relatively soft railway embankment. Glen said: “Due to the added resistance caused by the expansion process when bursting the existing pipe, the pit face had to be very robust. The set-up ultimately consisted of driven sheet piles with 13 mm (½ in) thick steel road plates.”
Works were carried under the normal working times of the trains. RETB tokens of the OBN2 line between Dalmally station and Connel station were taken and pipe pulling operations to install the new pipe took place between trains. The contractor also continuously monitored the cant and level of the track so that the works could be stopped at the first sign of any movement. The depth of the fill between the pipe installation and the track allowed sufficient consolidation through the embankment such that during the operation no track movements occurred.
Glen went on to say: “Due to the depth of this culvert below the track level, the traditional deep excavation and replacement would not have been feasible. With guidance and training from U Mole we were able to exploit the benefits of trenchless technology. We were able to cut down on our material usage in terms of not requiring substantial amounts of backfill and we minimised our wastage by having no excavated material to dispose of. Any opportunity where we are able to keep the railway open to traffic whilst undertaking this type of work puts us ahead of our competition and allows us to achieve a more economical and sustainable end result for both Carillion and ultimately Network Rail and the service’s customers.”
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Groundforce
Otley Road
HG3 1UD Harrogate
United Kingdom
Phone:
+44 1423 852 295
Fax:
+44 1423 536731