No run of the mill mission on the Florida coast near Miami
Oct 12, 2016
In February 2016 construction company Bessac completed work on a protection tunnel in extremely difficult geology in South Florida. In just ten months and using a customized machine designed especially for the mission, a "Herrenknecht Combined Shield" (HCS, diameter 3.13 m), 1,613 meters were tunnelled adhering to the highest safety standards. A new sewer line was installed in the finished tunnel – after half a century in use the old pipe was simply worn out.
The ground conditions and project circumstances of the mission at Norris Cut were anything but standard. Not only did the karstified, permeable geology pose the risk of flooding the machine. The complex Fort Thompson Formation to be tunnelled through was also full of sand-filled cavities. The tunnel face was therefore prone to instability.
For this reason the construction of the protection tunnel for a new sewer line between Virginia Key and Fisher Island required a special and highly flexible machine with exceptional safety features. A Herrenknecht Combined Shield offered the necessary adaptability: available in slurry mode as well as in EPB mode depending on the requirements, the HCS machine is optimally prepared for changeable ground conditions.
Additionally, the front area of the machine had to be accessible at all times during the challenge off Miami to allow for tool changes, for instance. For maximum safety a bulkhead with a dive pit was developed especially for the project. Thanks to the bulkhead between the front two machine parts and the overpressure thus enabled, muck and water cannot penetrate into the machine at the tunnel face. Should high water pressures nevertheless lead to flooding, the dive pit allows safe locking into the flooded area.
In the end the safety reserves were not needed. Neither the sophisticated lock system nor the EPB mode of the HCS machine were used. The ground was highly permeable as expected, however the proper design of the cutterhead and the appropriate disc cutters enabled the customer to perform only one maintenance stop, performed under compressed air after a novative ground treatment from the TBM.
"Dorsey" began the drive near the treatment plant on Virginia Key in April 2015. Right from the very first meter the project was characterized by its special requirements: to save space, with a diameter of twelve meters the launch shaft was rather small. At the beginning there was no room for the HSC machine's back-ups and they were only able to be used one by one after 70 meters of tunnelling. For the first section the TBM was therefore pushed forward in pipe jacking mode using a jacking frame adapter developed by the customer, the rest of the tunnel was then lined with concrete segments.
At a depth of up to 21 meters below sea level, the 3.13 meter diameter "Dorsey" dug its way forward in the months that followed. After 227 working days came the breakthrough on Fisher Island on February 16, 2016 – top performances of up to 24 meters per day and about 300 meters per month confirmed the optimum configuration of the TBM. By the end of the year the new 60" discharge pipeline is due to be installed in the finished protection tunnel and put into operation.
The successful drive on the Norris Cut project has pushed the boundaries of what is possible in Florida's tunnelling industry and contributed to its further development: "The project has set standards for work in Florida's underground and showed solutions for deep sewer lines in the porous Fort Thompson Formation," confirms Bernard Theron, President of Bessac.
With the construction of the Port Miami Tunnel already, machine technology from Herrenknecht had demonstrated that even the most complex ground conditions such as the Fort Thompson Formation can be safely mastered with optimally adapted technology. Despite its huge diameter of nearly 13 meters, in 2013 the EPB Shield S-600 reached its target reliably thanks to an additionally installed slurry circuit. According to internationally renowned accounting and consulting firm KPMG, in 2012 the Miami Port Tunnel was one of the ten most innovative transport projects in the world.
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Herrenknecht AG
Achim Kühn
Schlehenweg 2
77963 Schwanau
Germany
Phone:
+49 (0) 7824 302-5400
Fax:
+49 (0) 7824 302-4730