Pipe Express®: fast installation through groundwater near Stockholm

May 21, 2015

Herrenknecht's newly developed semi-trenchless method for pipeline installation has completed its third successful mission. South of Stockholm, using Pipe Express® Züblin Scandinavia AB installed a water pipeline more than a kilometer in length within twelve days. Groundwater lowering was not required despite a water level just below the terrain's surface. Compared to conventional open-cut construction the method has significantly less impact on the environment, while simultaneously minimizing costs.

The benefits were obvious to Mats Ohlsson, project manager of client Stockholm Vatten: "For open-cut construction we would have needed sheet piles and we would have had to lower the groundwater." The Pipe Express® method from Herrenknecht, however, requires no lowering of the groundwater. The construction company made the most of this enormous budget and time advantage. It used Pipe Express® for the laying of a 1,036 meter long section of a 48-inch water pipeline near Huddinge, some 10 kilometers south of Stockholm.

After drilling started on February 22, on March 5, 2015 already the destination had been reached. In the most productive 12-hour shift, 221 meters of pipeline disappeared into the ground; the average construction performance was 0.70 meters per minute. About 60 percent of the construction time was taken up just with welding and coating the up to 224 meter long steel pipe strings.

Michael Lubberger, Senior Product Manager Pipeline at Herrenknecht, is proud of the success in Sweden: "After the pilot project in the Netherlands and the subsequent deployment in Thailand, this is already our third drive with Pipe Express®. We see strong potential for the new method on the pipeline market." The keen interest of international specialists on the site confirms this view.

Pipe Express® from Herrenknecht is a new, semi-trenchless near-surface pipeline installation method. In this method, a buggy with a trenching unit creates a narrow, approximately 40 centimeter wide trench on the surface. Below it in the soil a boring machine is mounted that digs the actual tunnel with diameters of up to 1.50 meters and lays the pipeline at the same time. The excavated soil is brought to the surface by the trenching unit and backfilled in the trench again behind the machine, laborious finishing work is not required. The pushing force for both excavation unit and pipeline is provided by a Herrenknecht Pipe Thruster located at the starting position.

In contrast to the conventional construction method the corridors, including construction paths, are up to 70 percent narrower. Extensive earthworks, groundwater lowering, the ramming of sheet piles etc. are not necessary. Up to 2,000 meter long pipelines with a diameter of 900 – 1,500 millimeters (36" - 60") can thus be laid quickly and cost-efficiently.

The company Stockholm Vatten produces around 370,000 m³ of drinking water daily for the 1.3 million residents of the Swedish capital. Züblin Scandinavia AB were contracted to add one kilometer of pipeline south of Stockholm to the existing network.

Pipe Express® Albysjön 48“ water pipeline

Machine Data

Machine type: Pipe Express®

  • Newly developed semi-trenchless method for pipeline installation
  • Pipeline installation in a single step
  • Drive lengths up to 2,000 m
  • Pipeline diameters: 900 – 1,500 mm (36"– 60")
  • Overburden: 500 – 2,500 mm
  • Advance rates up to 1.2 m/min

Project Data

Project: Albysjön 48“ water pipeline
Application: Water pipeline
Pipeline length: 1,036 m
Pipeline diameter: 48"
Geology: water-saturated clay soil / soft sediment
Client: Stockholm Vatten AB
Contractor: Züblin Scandinavia AB

 

Contact

Herrenknecht

Achim Kühn

Schlehenweg 2

77963 Schwanau

Germany

Phone:

+49 78247 302-5400

Fax:

+49 7824 302-4730

E-Mail:

pr@herrenknecht.de

Internet:

To website