Shieldhall Tunnel in Glasgow reaches half way stage
Jul 14, 2017
Construction of the biggest waste water tunnel ever to be built in Scotland has reached the half-way stage in May 2017.
Scottish Water’s flagship Shieldhall Tunnel project, in the south of Glasgow, passed the milestone end of May when the state-of-the-art tunnel boring machine (TBM) building it reached a point under Pollok Park.
The £100m tunnel, which will enable Scottish Water to improve water quality in the River Clyde and tackle flooding, will at 3.1 miles long be five times longer than the Clyde Tunnel. Engineers working on the 1000 tonne, 180-metre-long TBM, started construction when it was launched last July and are expected to complete it later this year.
On May 1st they installed a full circle of giant concrete rings that form the tunnel at a point about 10 metres (about 32 feet) under the east of Pollok Park that is 1.55 miles along the route - the exact midway point of the tunnel.
Having reached the half-way stage, the work so far has produced some amazing facts and figures including:
- More than 1600 concrete rings of the tunnel (which are 1.5m-long) have been completed - each made up of six curved pre-cast concrete segments weighing 2.5 tonnes each which create a full circle when installed.
- More than 150,000 tonnes of earth, stone, clay and other aggregates has been excavated.
- More than one million man hours of work have been completed on its construction.
- The first half of the tunnel would be able to store the equivalent in waste water of 18 Olympic-sized swimming pools.
- More than 90% of the excavated material will be recycled.
- More than 7.5 miles (12 km) of pipes have been installed in the first half of the tunnel to service the TBM with air and water.
Paul Kerr, Scottish Water’s capital investment general manager, said: “We are delighted to have reached this milestone half-way stage in the tunnel construction.
“The Shieldhall Tunnel team includes some of the best and most experienced tunnellers in the world and they are making great progress with what is the biggest project of its type Scottish Water has ever undertaken.”
The TBM is tunnelling at a speed of about two millimetres per minute, with a rotating cutting wheel with 25 cutters at the front, through challenging ground which includes boulders, clay, hard sandstone, glacial tills and old coal workings.
The first half of the tunnel construction has taken it under Bellahouston Park, the Glasgow Paisley Canal railway line and the M77.
As it inches its way along the route, preparatory work is progressing at Queens Park where, in the past few days, work has been continuing on the construction of an exit shaft for the TBM and a smaller tunnel from that shaft to another shaft which will use a newly-installed flume to connect the tunnel to the existing network.
The route of the tunnel was chosen to maximise the use of parkland and minimise disruption.
The tunnel, which at 4.7 metres in diameter will be big enough to fit a double decker bus inside, is a key part of Scottish Water’s £250m, five-year programme of work, launched in 2013, to improve river water quality and the natural environment.
The programme is the biggest investment in the Greater Glasgow area’s waste water infrastructure in more than a century.
The tunnel will enable Scottish Water to improve water quality in the River Clyde and its tributaries and tackle flooding in various parts of the south of Glasgow area.
The team building the Shieldhall Tunnel for Scottish Water, known as the Glasgow Tunnel Partnership, is a commercial joint venture between Costain and VINCI Construction Grands Projets (corr.) called CVJV. Costain and VINCI have been involved in some of the world’s major engineering projects, including the Channel Tunnel.
For more information: www.scottishwater.co.uk/glasgow
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Scottish Water
Castle House / 6 Castle Drive / Carnegie Campus
KY11 8GG Dunfermline
United Kingdom