Water pipeline from Turkey to Cyprus - 1,600 mm diameter PE 100 pipeline and its flange-technology solution
Jul 24, 2014
Planning, dimensioning and construction » Pipe installation
The use of polyethylene pressure pipelines is gaining ever greater international regard and becoming ever more sophisticated.The reasons are diverse, and include this material‘s excellent resistance to corrosion, the flexibility of PE 100 pipes, and the resultant installation and cost benefits.
The construction of the 80 km long drinking-water pipeline through the Mediterranean sets new standards in water supply. Urgently needed by the Turkish Republic of Northern Cyprus (TRNC), it runs from the Turkish mainland (Mersin province) to the Turkish part of the island of Cyprus. Single lengths of 500 m PE pipe are being produced for the TRNC project, and installed tethered to float around 250 m below the surface of the Mediterranean. The otherwise customary seabed installation was not the first-choice solution for this project. One of the reasons was the depth exceeding 1,400 m, interspersed with numerous underwater ridges and trenches, encountered along the installation route.
The plans for this project go back more than fifteen years. The Alaköprü dam at the Turkish side was planned as early as 1998; the installation of the PE 100 pressure pipeline is now merely the conclusion of a long chain of events. Construction of the dam began in the mountains of the province, to the north-east of the Mediterranean town of Anamur, in 2011. The dam is also to be used for the generation of hydroelectric power, as well as storing the water required for the pipeline. From here, the water is transported by pipeline to the Anamur pumping station, and then enters the pressure PE line leading into the Mediterranean. After travelling around 80 km through the sea, the PE pressure pipeline reaches the coast of the Turkish Republic of Northern Cyprus, where the water is pumped into the reservoir of the Geçitköy dam, some 3 km way.
This unique PE project starts in the immediate vicinity of the Taşucu containment basin. Here, the 500 mm lengths of PE 100 pressure pipe sections, with an outside diameter 1,600 mm, have already been under production for many months. Three extrusion machines have been operating in parallel in this purpose-built facility. This system not only achieves cost benefits, but also for many projects, it provides an assurance factor both desirable and in many cases mandatory. The pipe length results from the fact that PE pipes, due to their specific gravity of less than 1 g/cm3, would normally float on the surface of the water. This fact, in combination with the lower relative density of freshwater compared to seawater, causes enormous positive buoyancy forces. These are counteracted by the pipe joining yokes, each consisting of two flanged connectors and a steel pipe bend to which the flanged connector is fixed. The steel yokes have an outside diameter of 1,514 mm, a curvature radius of 8,000 mm with a bend angle of 30°, and weigh around 10 tonnes without the connecting elements. Total weight including the two connecting elements is around 13 tonnes. The steels yokes, which also act as fixing and anchoring points, are subsequently drawn down to a depth of 250 m by means of steel cables and then anchored to the seabed (Figure 1), illustrating even better the special features of this project.
The specially made flange connectors are welded on to the long PE pipes on site and bolted to the steel pipe yokes by means of a steel flange provided specifically for this purpose. This yoke is then anchored to the seabed by means of steel cables to the securing and anchoring point. The challenge for Reinert-Ritz was that of providing a product to join the PE pipes and steel yokes durably and securely such order that even the most adverse conditions encountered underwater in the Mediterranean could not impair the connection. At a depth of around 250 m, this design involves the following technical challenges: buoyancy forces exerted by the PE 100 pipeline; powerful and dynamic sea currents, high shipping (and submarine) traffic frequency, potential of earthquakes, and the 7 bar operating pressure.
Decision for high quality and safety
The Nordhorn company is the specialist for semi-finished products and full pressure rated fittings conforming to the specified pressure classification for large dimensions up to an outside diameter of d 2000 mm; hence the right address for solutions to demanding problems. With over forty years of experience in plastics and the company’s pronounced quality awareness, the definitive arguments are established for initiating the co-operation between the project planner and Reinert-Ritz. From the high-quality granulate, used for production of the semi-finished products, through to the machining of the finished stub ends, the company was able, with its all- encompassing Quality Assurance system, to guarantee the high production standards vital for the performance and completion of this demanding project. This high quality consciousness has been shaped, in particular, by work for the gas industry in Germany, one of the first customers for PE, which makes use of this material and its high flexural strength in areas subject to mining subsidence. Only then did the safety and cost benefits result - within just fifty years - in PE‘s leadership on the supply-systems market.
It is therefore not surprising that ever more positive experience is being accumulated, with the application of PE pressure-pipe systems in large-scale industrial fire-extinguishing installations and power-generation plants, including the nuclear-energy industry.
There are two production routes for these full pressure- rated fittings: injection moulding and machining. The hollow bars and solid rods made by Reinert-Ritz are used in the latter process. This method assures a product free of voids and incorporating more than forty years of design and processing experience.
Solution of the complex flange concept
Production of hollow bars of 1,900/1,400 mm, with a wall thickness of approx. 250 mm, is the first stage in the fabrication of the special flanged connection. Subsequent machining takes place on a milling machine capable of processing material up to sizes of 2,800 x 1,500 x 4,800 mm. A particular challenge was presented by the large dimensions of the PE pipeline fitting and the extremely high dimensional accuracy demanded; tolerances of 0.0 mm and +0.5 mm. On site in Turkey, the finished PE 100 stub end is enclosed geometrically secured in two steel clamping assemblies, into which it must fit perfectly. The high-precision flanged connectors are assembled on a special installation ship, with twenty-four connecting bolts, on both ends of the steel yoke. The yoke is then anchored to the seabed, to enable the pressure pipeline to "float" at an average depth of 250 m.
Conclusion
The precondition for the success of this project was the successful evolution for the ultra-demanding innovative flange design of a PE 100 fitting which would durably join steel and PE 100. The extreme dynamic loads to which the flanged connection is exposed in underwater service were, above all, taken into account in development. Excellent communications and co-operation between Reinert-Ritz and the project planners achieved successful in-company installation and have generated an extremely high level of confidence for the longterm tightness and safety of the flanged connection.
(Authors: Dragisa Dubocanin, Paul Hutchings and Michael Ritz, Reinert-Ritz GmbH)
More News and Articles
Aug 28, 2024
News
ITpipes Secures $20M to Transform Water Infrastructure Management
ITpipes announced it has secured $20 million in equity financing from Trilogy Search Partners and Miramar Equity Partners.
Known for its trusted and user-friendly platform, ITpipes …
Aug 26, 2024
News
Professor Dr.-Ing. Dietrich Stein
With deep sadness we announce the loss of our founder and partner Prof Dr Dietrich Stein at the age of 85.
Engineers around the globe are thankful for his dedication to the inventions in the fields of sewers, …
Aug 26, 2024
News
PPI Releases New Installation Guide for PE4710 Pipe
PPI’s MAB-11-2024 Covers HDPE Water Pipelines Up to 60-in. Diameter and 10,000-ft Long Pulls
Developed by the Municipal Advisory Board (MAB) – and published with the help of the members of the …
Aug 23, 2024
News
Faster wide-scale leak detection now within reach
Mass deployment of connected leak loggers is being made possible by the latest technology, writes Tony Gwynne, global leakage solutions director, Ovarro
Water companies in England and Wales are …
Aug 21, 2024
News
Kraken awakens customer service potential in water
The innovative customer service platform Kraken has made a successful transfer from energy to water. Ahead of their presentation at UKWIR’s annual conference, Portsmouth Water chief executive …
Aug 19, 2024
News
Predicting the toxicity of chemicals with AI
Researchers at Eawag and the Swiss Data Science Center have trained AI algorithms with a comprehensive ecotoxicological dataset. Now their machine learning models can predict how toxic chemicals are …
Aug 16, 2024
News
Goodbye water loss: Trenchless pipe renewal in Brazil
Pipe renewal in Brazil
How do you stop water loss through leaks in old pipe systems without major environmental impacts and restrictions? The answer: with trenchless technology, or more precisely …
Aug 14, 2024
Article
Impact of high-temperature heat storage on groundwater
In a recently launched project, the aquatic research institute Eawag is investigating how the use of borehole thermal energy storage (BTES) affects the surrounding soil, the groundwater …
Aug 12, 2024
News
Watercare completes East Coast Bays sewer link
Watercare has successfully finished the final connection on the East Coast Bays link sewer at Windsor Park in New Zealand.
Much of the East Coast Bays sewer link was installed using horizontal directional …
Aug 09, 2024
Article
Innovative water solutions for sustainable cities
Cities need to become more sustainable and use their water resources more efficiently. Managing water in local small-scale cycles is one possible solution. A new white paper by Eawag, the University …
Aug 07, 2024
Article
How digital technologies contribute to universal drinking water
Digital water technologies have an important role in ensuring universal access to safe drinking water by 2030, that is according to a new report from the World Health Organisation. …
Aug 05, 2024
News
Knowledge transfer on sustainable water infrastructure in India
India’s fast-growing cities need an efficient infrastructure for water supply and wastewater disposal. A research cooperation, is therefore supporting the development of a sustainable …
Contact
Reinert-Ritz GmbH
Dragisa Dubocanin
Ernst-Heinkel-Straße 2
48531 Nordhorn
Germany
Phone:
+49 (0) 5921 8347-0
Fax:
+49 (0) 5921 8347-25